5.6 Input Test

Input Test (PLC Operands) Customer: Sheet: 1/1
Control Manufacturer: Siemens Customer No.: Date: 30.11.2006
Control Type: S7 Order No.:
Plant No.: Order Ref.: Conversion of two HPS conveyor belt models to three-phase drive and control via PROFIBUS-DP

 

Device to be tested:
PLC Operand:
Status
of Operand:
Matches Assignment List?
S1 HPSF_1_stop Normally Open
0
E0.0
1
Ok
S1 HPSF_1_stop Normally Open
1
E0.0
0
Ok
S2 HPSF_1_right_slow Normally Closed
0
E0.1
1
Ok
S2 HPSF_1_right_slow Normally Closed
1
E0.1
0
Ok
S3 HPSF_1_right_fast Normally Closed
0
E0.2
1
Ok
S3 HPSF_1_right_fast Normally Closed
1
E0.2
0
Ok
S4 HPSF_1_left_slow Normally Closed
0
E0.3
1
Ok
S4 HPSF_1_left_slow Normally Closed
1
E0.3
0
Ok
S5 HPSF_1_left_fast Normally Closed
0
E0.4
1
Ok
S5 HPSF_1_left_fast Normally Closed
1
E0.4
0
Ok