5.6 Input Test
| Input Test (PLC Operands) | Customer: | Sheet: 1/1 |
| Control Manufacturer: Siemens | Customer No.: | Date: 30.11.2006 |
| Control Type: S7 | Order No.: | |
| Plant No.: | Order Ref.: Conversion of two HPS conveyor belt models to three-phase drive and control via PROFIBUS-DP | |
| Device to be tested | PLC Operand |
Status of Operand |
Matches Assignment List |
|||
| S1 | HPSF_1_stop | Normally Open | 0 | E0.0 | 1 | Ok |
| S1 | HPSF_1_stop | Normally Open | 1 | E0.0 | 0 | Ok |
| S2 | HPSF_1_right_slow | Normally Closed | 0 | E0.1 | 1 | Ok |
| S2 | HPSF_1_right_slow | Normally Closed | 1 | E0.1 | 0 | Ok |
| S3 | HPSF_1_right_fast | Normally Closed | 0 | E0.2 | 1 | Ok |
| S3 | HPSF_1_right_fast | Normally Closed | 1 | E0.2 | 0 | Ok |
| S4 | HPSF_1_left_slow | Normally Closed | 0 | E0.3 | 1 | Ok |
| S4 | HPSF_1_left_slow | Normally Closed | 1 | E0.3 | 0 | Ok |
| S5 | HPSF_1_left_fast | Normally Closed | 0 | E0.4 | 1 | Ok |
| S5 | HPSF_1_left_fast | Normally Closed | 1 | E0.4 | 0 | Ok |